Troubles in India’s ambitious Light Combat Aircraft (LCA) project has
inflicted gaping wounds where it would hurt the Indian Air Force (IAF)
the most—the future plans for an Advanced Medium Combat Aircraft (AMCA).
The
Ministry of Defence (MoD) has “put on hold” the AMCA project that is
being spearheaded by Defence Research and Development Organisation’s
(DRDO) Aeronautical Development Agency (ADA).
The reason for the
sudden decision to send the AMCA project—which began in right earnest in
2006 as the Medium Combat Aircraft (MCA) development in 2006—to cold
storage is to help ADA to focus all its energies to first work on
completing the much-delayed LCA project. “The AMCA has been put on hold
for the moment. This decision was taken recently to let the ADA focus on
the LCA project,” top Defence Ministry sources told The Sunday
Standard. The AMCA project, for which the IAF provided the final Air
Staff Qualitative Requirements (ASQR) in April 2010, may be taken up at a
later date, sources said. But that will still be far away in the
future.
India will buy Rafale planes from the French Dassault
Aviation as part of its 126 Medium Multi Role Combat Aircraft (MMRCA);
in the tender there is a provision to buy another 63 as a follow-on
order. That apart, India is working on the Fifth Generation Fighter
Aircraft (FGFA) in collaboration with Russia. With the final agreement
on the design and development of the FGFA three months away, India will
get at least 140 FGFAs for induction by 2027. Considering that most of
the capabilities of AMCA will be covered by the MMRCA and FGFA planes,
the revival of the AMCA will be a well thought-out one, sources said.
The
AMCA’s envisaged features include stealth, multi-role operations,
adequate precision strike capabilities, including critical first-day
missions such as Suppression of Enemy Air Defence (SEAD) and Destruction
of Enemy Air Defence (DEAD).
The much-touted Tejas has taken 30
years already, at an escalated project cost of Rs 5,489 crore. Since the
LCA project was sanctioned in 1983 at a cost of Rs 560 crore, the time
overrun has resulted in a 10-fold increase in the project cost. The
plane is yet to get even its Initial Operational Clearance (IOC) so that
the IAF could take the plane for a spin. But sources pointed out that
the LCA still lacks certain critical capabilities, including a reliable
radar, and is deficient in at least 100 technical parameters. “The plane
cannot fly on its own. It needs a lifeline in the form of support and
monitoring of its systems from the ground by technicians,” they said.
The
LCA, in fact, gave creditable flying displays during the AeroIndia show
in Yelahanka in Bangalore in February this year, and followed it up
with weapons firing to hit both ground and aerial targets during the
Iron Fist fire power display by the IAF in the Rajasthan’s Pokhran
ranges, again in February this year. “The common man thinks the plane is
doing fine, its engine sounds great and the manoeuvres are perfect. But
those flying and weapons firing displays are done with ground
monitoring and support. The plane is still not ready to flying on its
own,” sources stressed. Their guess is the LCA may not meet its schedule
of obtaining the IOC before July this year and it could take till
December this year or early next year before it is ready. To give an
example of LCA’s troubles, the sources noted that LCA was grounded for
three months between September and December 2012 following problems with
its landing gear. “Normally, a combat plane is ready for its next
sortie following a 30-minute attention from ground service personnel
soon after it has returned from a mission. In the case of LCA, after a
single sortie of about an hour or so, it needs three days of servicing
before it can go for its next sortie,” they said.
At present, the
IAF has placed an order for 40 LCAs Mk1 to raise two squadrons by
2016-17 with HAL which is the nodal agency for production of Tejas. But
these will be delivered with the American General Electric F404 engines
which provide only 80 Kilo Newton power.
Later, 80 more LCAs of
its Mk2 version will be ordered for raising four more squadrons. The LCA
Mk2 will be powered by the GE F414 engines that provide a 90 Kilo
Newton thrust.